  • Vinci Construction Grands Projets - Plant Engineer

    Rueil-Malmaison Cedex 2012 - maintenant Egypt - Assiut: Dam construction during 2 months, to make the hand-over between two plant managers
    Hong-Kong: Tunnel construction during 3 months, for the start of the project.
  • IFP - Trainee

    CHAMBRAY LES TOURS 2008 - 2008 Reduction of the vibratory level of an automotive engine.
  • Vinci Construction Grands Projets - TBM (Tunnel Boring Machine) Mechanical & Methods Engineer

    Rueil-Malmaison Cedex 2008 - 2012 TBM (Tunnel Boring Machine) mechanical enginner on the construction of a tunnel in Hallandsas, Sweden.
    - Follow-up of the maintenances and modifications on the TBM.
    - Follow-up of the team in charge of the maintenance of the TBM.
    - Follow-up of the dismantling, transfert and re-assembly of the TBM (200m long, 10m wide) between the first and the second tunnel.
    - Responsible of the methods and planning for the dismantling of the tunnel utilities (7,5km of equipments done in 5 weeks).
    - Design and development of a web-site and database to follow and record all the interventions on the TBM.
    - Contact with the suppliers.
    - Responsible of the rescue chamber training.
  • Hwaseung R&A - Trainee

    2007 - 2007 Optimization of the thickness of the inner panel of an automotive door, for Hwaseung R&A (Yangsan, South Korea).